HomeMy WebLinkAboutO'Dell Engineering Inc, - 1st Amendment to Agreement dated 05.03.23 - Play Structure Improvements Project - 08.24.23FIRST AMENDMENT TC AGREEMENT
THIS FIRST AMENDMENT TO AGREEMENT (Amendment) made and entered
into as of this ZL+' day;of 2023, amends the Agreement entered into
between the CITY OF FRESNO, a California municipal corporation (City), and O'Dell
Engineering Inc., a California corporation (Consultant);
RECITALS
WHEREAS, City and Consultant entered into an Agreement dated May 3, 2023,
for professional architectural and engineering services (Agreement); and
WHEREAS, City and Consultant now desire to modify the scope of work therein
by requiring additional services; and
WHEREAS, by entry into this Amendment, the Consultant agrees it has no claim,
demand or dispute with the City.
AGREEMENT
NOW, THEREFORE, in consideration of the above recitals, which recitals are
contractual in nature the mutual promises herein contained, and for other good and
valuable consideration hereby acknowledged, the parties agree that the Agreement be
amended as follows:
1. Consultant shall provide additional services as described in Attachment A,
attached hereto and incorporated herein by reference. Such additional services shall be
rendered within the term of the Agreement and completed no later than July 1, 2025,
following execution of this Amendment by both parties.
2. Consultant's sole compensation for satisfactory performance of all services
required or rendered pursuant to this Amendment shall be a total fee of Thirty -Seven
Thousand dollars ($37,000.00).
3, In the event of any conflict between the body of this Amendment and any
Exhibit or Attachment hereto, the terms and conditions of the body of this Amendment
shall control andl take precedence over the terms and conditions expressed within the
Exhibit or Attachment. Furthermore; any terms or conditions contained within any Exhibit
or Attachment hereto which purportto modify the allocation of risk between the parties,
provided for within the body of this Amendment, shall be null and void.
4, . Except as- otherwise provided herein, the Agreement entered into by City
and Consultant, dated May 39 2023, remains in full force and effect. The services of the
Consultant as described in -Attachment A are to commence upon the City's issuance of a
written "Notice to Proceed."
IN WITNESS WHEREOF, the parties have executed this Amendment at Fresno,
California, the day and year first above written.
CITY OF FRESNO,
a California municipal corporation
By:
RANDALL W. MORRISON, PE
Assistant Director
Public Works Department
APPROVED AS TO FORM:
ANDREW JANZ
City Attorney
By:
TAYLO R R H Digitally signed by TAYLORRH
Date: 2023.08.15 14:24iD4�24:06-07'00'
Taylor W. Rhoan Date
Deputy City Attorney
ATTEST:
TODD STERMER,
City Clerk
O'Dell Engineering, INC.,
a California Corporation
By:
Name: OiLAt Gt+'-Awlyc" -
Title: ?IL%
(If corporation or LLC., Board Chair,
Pres. or Vice Pres.)
By: - Name -
Title:
(If corporation LLC., CFO,
CMC Treasurer, Secretary or Assistant
Secretary)
By: a��
3
ate
Addresses:
CITY:
City of Fresno
Attention: Armando Cervantes
Engineer 1
2600 Fresno Street, Room 4016
Fresno, CA 93721
Telephone No. 559-621-8687
Attachment: Attachment A
2
REVIEWED BY:
:
FRANCISM �,,....CN..ANC=M.
. or�•�• �9o«o.�im.�i:.oc.usr�
Francisco V. Magos II, PE, MBA, QSD
Site Development Manager
Public Works Department
CONSULTANT:
O'Dell Engineering Inc.,
Attention: Chad Kennedy, P.L.A, CPSI,
LEED AP BD+C, Principal -in -Charge
1165 Scenic Drive, Suite A
Modesto, CA 95350
Telephone No. (209) 571-1765
Email: ckennedy@odellengineering.com
Attachment A
ADDITIONAL SCOPE OF SERVICES
Consultant Service First Amendment to Agreement between City of Fresno (City) and
O'Dell Engineering, Inc., (Consultant)
Play Structure Improvements Project
Scope of Work
Additional Scope of Services includes but is not limited to: developing plans and bid
documents for the construction of play structure improvements at Logan Park within the
city of Fresno. The project scope shall include: new soft fall safety surface, assessing
existing conditions of the play structure and equipment, and assessment and
recommendations for accessibility at Logan Park.
Coordination Meetings
The CONSULTANT will meet with CITY staff a total of two (2) times during the design
process: The first meeting will be on -site and shall occur after the Notice to Proceed (NTP)
for Part One is issued: The second meeting shall occur following Schematic Design
submittal and issuance of NTP for the Design Development and Construction Document
Phase. Meeting agendas and minutes will be provided for each meeting.
The CONSULTANT shall, at the first meeting, meet on -site with CITY staff as part of the
project initiation. This well -run organizational meeting will initiate CONSULTANT'S
proprietary client communication program and the following typical items will be
discussed:
1. Introduce staff and project partners to the design consulting team.
2. Review objectives of the project, scope of services, deliverable expectations,
project schedule, and milestones.
3. Confirm project parameters and limits of work. (Conduct a site review and photo
document site conditions).
4. Collect available data and published material.
5. Establish meeting and presentation schedules, and communication channels with
all parties involved.
6. Review and list all applicable design/planning standards, opportunities, and/or
challenges anticipated,
7. Coordinate with agency departments, other agencies, and stakeholders.
8. Review project budget and billing requirements.
9. Complete custom client communications program.
Site Analysis/Data Collection & Review
Preliminary Investigation
1. Research objectives will include a detailed review of project history and existing
park site information including prior building history and soil studies. A site visit will
be conducted and site photographs will be taken.
3
2. Contextual Analysis —Analyze existing elements within the proposed site to guide
design. Items such as prevailing winds, soil type, local demographics, as -built
drawings, utilities, etc. will be reviewed.
3. Topographic Survey Review
4: ADA Compliance Assessment and Recommendations
5. Existing Play Structure Assessment and Recommendations
Schematic Design
Following the site analysis phase; the CONSULTANT will prepare a schematic design
development plan set. The design development plan will include the following:
1. A site concept plan, to scale, overlayed on existing topographic shots -
2. ADA path of travel compliance assessment and recommendations
3. Play structure review and repair/replacement options
4. Preliminary selections for site furnishings and finishes
5. Supporting graphics
6. Preliminary cost estimates
a. Including cost estimates for both repair and replacement where play
structure assessment is included in the scope
The CONSULTANT shall make as many submittals as may be necessary or desirable to
obtain the acceptance by the City and shall assist the CITY in applying for and obtaining
from applicable public agencies any approval permit, or waiver required by law, which
assistance shall include, but not be limited to, making PROJECT information available to
the CITY.
Design Development and Construction Documents
Following the approval of the schematic design documents and issuance of a written
Notice to Proceed with this Part Two, the CONSULTANT will prepare a final site
improvement plans for planning approval and permitting. Improvement plans will include
routine information normally required by the city of Fresno. The scope of work will include
two packages - 90% construction documents with updated technical specifications and
estimates, and 100% documents including final specifications and estimates. This service
may include the following as applicable:
1. Project information
2. Site plan
3. Title sheet
4. Existing conditions and demolition plan
5. Tree protection plan (ISA Arborist reviewed)
6. Underground utilities plan
7. Grading and drainage plan
8. SWPPP and erosion control plan
9. Horizontal control plan
10. Site finishes and furnishings plans
11. Enlargement plans (playground, etc.)
12. Irrigation plans and water use calculations
13. Planting plan
14. Construction details
a. Shade structure sections, plans, and details
4
15. Construction quantities and estimates
16. Technical specifications, city will provide boilerplate specifications
Following approval of the 100% PS&E drawings, the team will prepare a final bid package.
The bid package will include:
1. Final stamped drawings
2. Front end documents
3. Stamped and signed cover sheet
4. Bid forms
5. Bid item descriptions
6. Final technical specifications
The CONSULTANT shall make as many submittals as may be necessary or desirable to
obtain the acceptance by the City and shall assist the CITY in applying for and obtaining
from applicable public agencies any approval permit, or waiver required by law, which
assistance shall include, but not be limited to, making PROJECT information available to
the CITY.
Bidding & Construction Support
Bid Services - CONSULTANT will perform bidding and contract award services to assist
the CITY with selecting the appropriate contractors and product manufacturers. Within
the budgeted allocation and upon the request of CITY staff, services rendered shall
Include:
1. Responses to RFIs
2. Attendance at the pre -bid meeting
3. Preparation of Addenda and Transmittals (as needed)
Construction Support Services - CONSULTANT will perform construction support
services throughout the project's completion. Within the budgeted allocation and upon the
request of City staff, services rendered shall include:
1. -Preparation and maintenance of construction schedule
2. Attendance at the pre -construction meeting
3. Review and approvals of contractor's schedule, RFI's, shop drawings, and
submittals
4. Construction observation site visits (2 max per site)
Compensation
Compensation for all services described above will be based on a percentage of the
construction costs. Fees will be billed monthly in accordance with work completed.
First Amendment Compensation
Part 1: Schematic Design (34%) $12,580.00
Part 2: Design Development and Construction Document Phase (52%) $19,240.00
Part 3: Bid Support Phase (7%) $2,590.00
Part 4: Constructlon and Contract Administration Phase 7% $2,590.00
TOTAL PROFESSIONAL SERVICES
5
Original Contract Amount
Part 1: Schematic Design (34%) $145,996.00
Part 2: Design Development and Construction Document Phase (52%) $223,288.00
Part 3: Bid Support Phase (7%) $30,058.00
Part 4: Construction and -Contract Administration Phase 7% $30,.Q58.00
TC]TAL PR.oFESSIONAL SERVICES FEE $429,400.00
Total Amended Contract Amount:
Schedule
Time allotted for each phase is summarized below.
Part 1: Schematic Design Phase
Part 2: Design Development and Construction Document Phase
Part 3: Bid Phase Assistance
Part 4: Construction Phase Assistance
$466,400.00
28 calendar days
No additional
duration required
No defined duration