FIRE INDUSTRY BULLETIN 2020-001
SCOPE
Updated fire sprinkler system acceptance/final permit signoff requirements for NFPA 13
and 13R fire sprinkler system installations.
PURPOSE
The purpose of this industry bulletin is to notify applicable stakeholders of the upcoming
modifications to FFD fire sprinkler system acceptance/final permit signoff requirements.
BACKGROUND
As noted in the California Fire Code (CFC), the fire code official has the authority to
formulate policies they deem necessary based upon local conditions related to fire
sprinkler system acceptance requirements.
To attempt to minimize some of the most common errors found during fire sprinkler final
inspections/system acceptance inspections, the Department has begun to require the
installing contractor to provide a completed and signed NFPA 13 Contractor's Material
and Test Certificate for aboveground piping. By requiring this form to be completed, it is
the Department’s intent to help installing contractors reduce the number of re-
inspections that have to be completed for errors or omissions at final inspection. This
form is also required as noted in NFPA 13 §25.1.
INFORMATION
Beginning February 10, 2020, all firms shall prepare and provide a completed and
signed NFPA 13 Contractor's Material and Test Certificate for aboveground piping. This
certificate shall be provided to the Department at fire sprinkler final inspection/system
acceptance, regardless of the date the permit was issued.
NOTE
This notice is effective January 24, 2020.