HomeMy WebLinkAboutT-3453 - Agreement/Covenant - 6/30/2006 AGREEMENT
In consideration of the acceptance of the offers of
dedication of the streets , highways, public ways, easements
and facilities as shown and delineated on said map, and the
approval of said map for filing and recording as provided
and required by law, it is mutually agreed and understood by
and between the Subdivider and the City, and the Subdivider
and the City do hereby mutually agree as follows:
4 . The Subdivider shall perform the work and improve-
ments hereinafter specified on or before November 30 ,
19 82 , to the satisfaction of the Director of Public Works
of the City. When a delay occurs due to unforeseen causes
beyond the control and without the fault or negligence of
the Developer, the time of completion may be extended for a
period justified by the effect of such delay on the comple-
tion of the work. The Developer shall file a written re-
quest for a time extension with the Director of Public Works
prior to the above noted date, who shall ascertain the facts
and determine the extent of justifiable delays, if any. The
Director of Public Works shall give the Developer written
notice of his determination in-writing, which shall be final
and conclusive.
5 . The work and improvements, more specifically shown
on the attached plans and made a part hereof, shall be done
in accordance with the construction standards contained in
the City of Fresno Standard Specifications adopted March 5,
1970 by Resolution No. 70-36 , and as amended at the sole
cost and expense of the Subdivider including all costs of
engineering, inspection and testing as specified in Item 12 .
6 . The work and improvements are as follows :
a. Construct all landmarks, monuments and lot
corners required to locate land divisions
shown on the Final Map.
"Pursuant to Section 66497 of the State
Subdivision Map Act, prior to the City' s
final acceptance of the subdivision and
release of securities, the subdivider shall
submit evidence to the City of Fresno of
payment and receipt thereof by the engineer
or surveyor for the final setting of all
monuments required in the subdivision. "
2
b. All utility systems shall be installed under-
ground. The subdivider ' s attention is directed
to the installation of street lights in accordance
with Resolution No. 68-187 and Resolution No. 78-
522. The subdivider shall construct a complete
underground street light system as approved by the
Traffic Engineer prior to final acceptance of the
subdivision. Height, type, spacing, etc. of stan-
dards and luminaires shall be in accordance with
Resolution No. 78-522 and shall be approved by the
City Traffic Engineer.
C. Water main extensions and services shall be pro-
vided in accordance with applicable provisions of
Chapter 14 , Article 1 of the Fresno Municipal Code
and all applicable charges shall apply.
d. Sanitary sewer extensions and services shall be
provided in accordance with applicable provisions
of Chapter 9, Article 5 of the Fresno Municipal Code
and all applicable charges shall apply.
e. Lot drainage shall be in accordance with Section
13-120. 7012 of the Fresno Municipal Code.
f. Any temporary storm water retention basins con-
structed or enlarged to serve this tract shall be
fenced in accordance with City standards within
seven (7) days from the time said basins become
operational or as directed by the Engineer.
g. Wet-Ties shall be in accordance with B-Job No. 9574 .
The amounts indicated as "Wet-Tie Charges" are esti-
mates only and serve as a deposit to cover the
actual cost of construction. Should the actual con-
struction cost be less than the deposit, the sub-
divider shall be refunded the difference. Should
the actual construction cost be greater than the
deposit, the subdivider shall be billed by the City
of Fresno for the difference and shall be directly
responsible for payment.
h. Perform and construct all work shown on the attached
plans. (City Drawing Nos. 10-C-4355 through
10-C-4361, Water Job No. 3373 , Nos. 15-C-4932
through 15-C-4936 and FMFCD Plan No. AK-1-1 through
AK-1-3) , unless specifically omitted herein.
i. The subdivider has deposited with the City the sum
of $124 ,539. 26 for the following:
J1 17.(oOS,yS
1. Inspection Fees. . . . . . . . . . . . . . . . . . . . . . . . . . . $
($17, 605.45 less $7 ,863. 20 paid with Early
Construction Agreement)
2. Intersection Signing, 5 @ $90. 00. . . . . . . . . . $ 450. 00
3. Traffic Regulatory Signing, 10 @ $35. 00. . . $ 350. 00
4 . Street Trees, 102 @ $77. 00. . . . . . . . . . . . . . . . $ 7 , 854 . 00
5. Plan Check Fees (Streets) . . . . . . . . . . . . . . . . . $ 844. 07
6. Pond Maintenance Fee. . . . . . . . . . . . . . . . . . . . . . $ 2 , 000. 00
7. Sewer Trench Water Compaction Charge,
6 ,925 C.Y. @ $0. 04/C.Y. . . . . . . . . . . . . . . . . . . . $ 277. 00
8. U.G.M. Traffic Signal Charge; (Zone E-4)
22. 93 AC. @ $300. 00/AC. . . . . . . . . . . . . . . . . . . . $ 6 ,879. 00
3
w ,
9 . U.G.M. Major Street Charge; (Zone E-4 )
22. 93 AC. @ $700 .00/AC. . . . . . . . . . . . . . . . . '. . . . . . $' 16 ,051 .00
10 . U.G.M. Grade Separation Fee;
(Service Area E-4-A) , 22. 93 AC. @ $1,500. . . . . $ 34 ,395. 00
11 . Sanitary Sewer Fees. . . . . . . . . . . . . . . . . . . . . . . . . . $ 6 , 312. 00
a. Oversize Charge; (Area 20)
26. 30 AC. @ $240. 00/AC. . . . . . $ 6, 312. 00
(Note: Major Facilities Fee
is to be Paid at Time of Development)
Total Sewer Charges. . . . . . . . . $ 6, 312 . 00
12. Water Charges. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 45 , 696 .94
a. Froftage
300 LF. @ $3.75/LF. . . . . . . . . . $ 1,125. 00
1, 323. 87 LF. @ $1 . 875/LF. . . . $ 2, 482. 26
b. Fire Hydrant Charge
853, 934 SF. @ $. 0125/SF. . . . . $10, 674 . 18
C. Transmission Grid Main
26. 30 AC. @ $375. 00/AC. . . . . . $ 9, 862 . 50
d. U. G.M. Well Development Charge
(Service Area No. 132)
26. 30 AC. @ $310. 00/AC. . . . . . $ 8, 153 . 00
e. "Wet-Tie" Charge. . . . . . . . . . . . $13 , 400 . 00
Total Water Charges. . . . . . . . . $45 , 696 . 94
13. Present Credits/Future Reimbursements
a. Water
Fire Hydrants - Future
5 @ $300. 00/EA. . . . . . . . . . . . . . $ 1, 500. 00
b. Sanitary Sewer
Estimated Oversize Main
Eligible for Refund. . . . . . . . . $14, 21� . 00
Extra Depth Credit. . . . . . . . . . $18 ,368 . 00
Present Credit -_ Oversize
Charge. . . . . . . . . . . . . . . . . . . ($ 6, 312 . 00) ($ 6 , 312 . 00
Estimated Future Refund. . . . . $2&,270. 00
(Based on Audit of "As-Built"
Quantities)
TOTAL FEES AND CHARGES. . . . . . . . . . . . . . . . . . . . . . . $124 ,539. 26
(Less Present Credits)
14 . Fee Deferments
A. Pursuant to Sections 12-4 . 508 and 12-4 . 509
of the Fresno Municipal Code, the following
fees are being deferred by the City through
a covenant executed by the subdivider :
1. U.G.M. Park Fee (Area 4)
26. 30 AC. @ $504 . 00/AC. . . . . . . . . . . . . $ 13,255. 20
4